Tech Staff Meeting Notes April 8, 2019
The top priority is always repair of down stations.
NM problem stations
ET problem stations
Duty Table updated October 2017
The Nth Annual Fish Fry will be Friday May 3, 2019.
Chris McGoldrick will retire as of June 30, 2019.
We will retire cell phone 5152 and use employee cell phone allowances instead.
USGS funding is in place for our three approved Deferred Maintenance items.
USGS may provide 2019 DM funds that would essentially replace all remaining older digital hardware.
NC is reviewing the GFM agreement
There will be a GPS week rollover (max week count exceeds 1024) in April 2019. While all our Reftek firmware is current, receivers are affected by the rollover. Stations affected: GNAR, LCAR, PARM, PEBM, PENM, HBAR, HENM, LPAR, MKAR.
SIS areas of responsibility
XP retirement. ET will be entirely digital by summer 2019 if all goes as planned. We need a plan for NM.
RTCC on Ubuntu 16 is able to get /parameters but fails with /status-control on loopback and RTPD hangs. It works in Ubuntu 18 but openvpn does not. Wait for that fix then leapfrog OS to 18.
The four wheeler is now in ET--a new one for NM is in house.
NMDown
Data taken from:
/dat1/seisadm/Working/NM/201904/20190404_000811_MAN
Down
CWPT.EHN
HTAR.EHN
MATM
MSAR.EHE
PPLM
TWAR
WYBT
NHIN.EH*
NHIN.HN*
HOPT.EHN
Misc
HOVM - spikes
AG Down
FCAR
There are 1 of 7 ISIS3 upgrades remaining (NHAR).
Make permanent repair receive mast for WYBT at HOPT install four 52 watt panel.
Strongmotion stations NAIT, SEAR, and NHIN are having trouble moving up the priority list. of the three, SEAR is most valuable. NHIN is probably a fuse but can wait until there is a new obisidian to replace the 5TD.
DBB:
MKTA:
LNXT:
Have a new engine control board to install in the generator at LNXT (aka the money pit).
NMAD:
AZTN/HDBR: Need to pull the 200' sensor at the weigh station. Probable water damage. There is no budget for this. Should we try to repair the sensor at MPHB and put it at HDAR2 (MPHB is over two decades old, possibly closer to three)? Should we turn off the HDAR2.*.20 channels until the sensor can be replaced?
CERI:
Server room power is unbalanced. Need to balance when three new AQMS machines
are racked.
IT scans flagged nori and folkworm, primarily due to apache. Turned it off on nori. Need to upgrade the Ubuntu OS but not while in produciton. There are several servers we can use to play musical chairs. James and Steve will take care of it.
The upgrade at CCRT still has loose ends.
Conversion to Digital
We have 4 USGS funded upgrades, and will have 9 remaining under the Choctaw
project. USGS deadline is 1/31/2020 so the Choctaw upgrades are the
priority
Need to determine the revised budget and acquire funding.
Geobits are working well
Still having trouble with the Cambium radios though John has a working pair. James will take another crack at it with John's configs. The GE links at RCGA and DYTN seem to be working well.
Replacement station for GTTN and RBNC needs a new plan. A cell modem would provide more options.
Need to remove antennas, coax, and any other hardware from the tower at
Greentop. John and Chris will schedule a trip.
ETDown
Data taken from:
/dat1/seisadm/Working/ET/201904/20190404_170940_MAN
Down
BCRT.HN*
GMG.HNN
Misc Problems
CPRT.HN* - huge gaps that occur frequently
CPRT.EH* - "
CPCT.HNE- spikes
VHTN.EHN - unusable
GFM - dropping out
CPRT has many gaps though the telemetry is solid. This is Phase I of the Choctaw Short-term Plan
STAR Node
After the ETT upgrade, the node can be rebuilt.
BCRT had an intermittent 40Hz spike.
Move PMTN due to excessive noise and vandalism. John has a site and sent a draft MOU to Mitch. The University did not ask for changes and asked for the WMA director to sign first, its currently in Nashville for approval. A portable was installed and shows no surprises, it should a good quiet site.
HPNC Node
MTTN Node
Bob has funds for a GPS station in ET. Because sky view is in short supply, we need Bob to identify a few sites. John will then scout those sites on the ground.
Eleven receivers for 2018 Deferred Maintenance arrived. Need to replace as trips allow. Funds (including travel) need to be spent by the end of May 2019. Necessary prep is complete and ready for deployment.
All GPS sites need PM visit.
There was an internet "upgrade" at MACC. Need to reconfigure GPS networking configs; James may be able to do it remotely.
Vilos is not in the allowed list of IP's for AR park internet access. Mitch will check with Cramer on shutting down smeagol and enabling its IP on a third NIC.
Z41A has a leaky vault. It will need to be replaced with a CERI style vault.
HHAR needs a bigger solar regulator. The new one should last a year.
The FDL wiki is here: https://umwiki.memphis.edu/display/FDL/CERI+FDL
The seisnet group on umdrive is at http://umdrive.memphis.edu/mwithers/seisnet You will need your uuid and password.
The seisnet wiki is at https://umwiki.memphis.edu/display/CERITech/CERI+Tech You will need your uuid and password.