Tech Staff Meeting Notes June 26, 2007
Current Top Priorities are: Station Maintenance. Mud-Island. Two new GPS stations. (Also wish to get INV populated.)
There are four levels of priority.
Priorities | Wish to try to get these done (or make progress on) before the next meeting (yeah right) |
Second Tier | Fit this in too if an opportunity arises. May be good to do instead of priorities but check with Mitch. Likely to be a priority in a previous and/or subsequent month |
As Time Permits | Fit these in when you can but not instead of first or second priorities |
Other | Stuff we hope to get to and don't want to forget about |
This task list as of September 12, 2006. Note that everyone is still needed to work on essentially all tasks. There is however, a single person who is primarily responsible for each one. Mitch of course, is ultimately responsible for everything.
The Fiscal Fish Fry will be friday, June 29, 2007. There are a total of 51 people signed up. 36 regular, 13 student, and 2 no fish.
Priorities
Station Maintenance, NMSZ
Several stations repaired. A bunch of single channel problems remain.
Lennox receive hardware and preamps replaced. Radios aligned, etc, etc.
Signal strength is much better. Might consider doing the same at nmad
and mkta.
Need a dual mux assembly or two. Have the AMUX64T's. Pat will build up
the rest of the hardware.
New Madrid high temp alarm went on the other day. The ceiling is hot.
Greg thinks he knows where to get Hypalon for the top of the roof. This
would insulate and waterproof and avoid having to repaint. Should also
go a long way toward keeping the inside cool.
MKTA needs an air conditioner in the doghouse.
Need a remote reset at lnxt. Current owner of the transmitter may
not be installing a reset similar to what wkno had so we may need to
install our own phone line. Steve suggested we get dsl while we're
at it for a dbb backup but the cheap dutchman isn't ready to do that yet.
I-40 Bridge.
Need an 8 inch extension for surface vault to get it above grade.
New 200' hole is 100' so far. Bill is keeping keeping us posted.
Looks like scream2ew doesn't work with the new dm24. We just get
binary hyroglyphics and Jim reports that the status streams look
different too. Al will test with scream2ew from ew 7.1 to make
sure that also doesn't work. Mitch will then contact Bruce.
After much griping from Mitch, it looks like
the best solution is to telemeter to the weigh station. From there
we get on the TDOT fiber network. We telemeter from the TDOT POP
at Boswell St (aka perimeter mall) to Richardson. A pc will be installed
at richardson (unless there is a viable switch solution to transfer from
private TDOT to CERI subnet). From there we hop on the CERI microwave
and suck the data into anssworm. Hopefully the project has sufficient
funds for the extra telemetry link (about $4k) and pc (about $1.5k).
Chris is arranging to have a fence installed (after any pad, gravel
or whatever is installed). Cost is $1100 installed (must be
real silver). We don't want to do it ourselves since it has to
tie into the existing dilapidated fence.
The number 3 recorder keeps losing gps lock.
The recorder disks need to be reformatted. This can't be done remotely.
The constant read/write to the fat file systems is going to make this
reformatting something that needs to be done periodically. Requires
physically going under the bridge to do it. Dont ya just love dos
and obsolete hardware?
The wireless resets seem to be getting noisy making it more tricky
than normal to reset.
GPS
Greg, Bob Smalley, James, Chris, Bill, and Mitch met on June 25, 2007
to discuss GPS issues. This was done outside the staff meeting set for
June 26 because otherwise the entire 6/26 meeting would have been
spent on GPS issues.
We're in the process of getting James out of the station maintenance business. GPS stations will be treated as any of the seismic network stations. Mac will be the lead for routine maintenance. Data handling and processing is still done by Bob et al.
Greg is in charge of getting anything done to the GPS stations to Steinerize them. This is necessary to make sure we can maintain them without burning alot of time on reapplying bandaids. Note that they are in pretty good shape already. The primary hassle is communications.
Greg has a couple options for improving communications.
Get permission from TWRA to put up a 50 or 60 foot tower at New Markham.
From there we can probably hit the New Madrid node. It would be best
to make it a 2.4G aironet shot so that its just an extension of the DBB.
This would get us real-time continuous access to LCHS, NWCC, RLAP, and
the new one at New Markham. the TWRA site is a concentrator for the four.
Can probably hit the lnxt node from STLE.
Not sure what to do about MAIR and CJTR.
Mitch noted that on the DBB, it is preferable to transfer less data more
frequently that more data less often. This helps avoid longer burst
periods that could slow down the real-time continuous seismic data.
The GPS data bandwidth isn't large but if you burst 24 hours worth,
it could cause a bunch of dropped seisnet packets.
James noted that the fans and filters need to be replaced at all sites.
Bob made the below notes in May. Greg will take the lead on monument install (which may be simply assigning tasks) after successful bid is in hand. He'll let Bob know when the comm etc, plan is finalized.
5/30/07 Install 2 new sites Select exact site LCHS - done New Markham - approx Get bids for monument Someone to supervise monument installation Someone to buy remaining supplies for monument installation Someone to weld monument after driller installed Build 2 boxes Spec solar requirements Lightning protection Install - monument then GPS and comms equipment Upgrade/maint remaining sites Install SCIGN domes on all sites (excuse to visit each one - plan so can do all other upgrades, etc. needed) Communicaiton at LHCS (immediately brings NWCC online) How to get power and internet (wire) to base of tower Internet service* Lightning protection Upgrade at RLAP Find burried stuff Trench Solar (5 watts for 2 weeks) Install box on tower Install comms on tower (need LCHS up and running first,may or may not make it back without repeat through New Markham) Lightning protection Communications at STLE Select antenna site at School Run cables Install Freewave Power and antenna at STLE Internet service* Lightning protection Communications at CJTR Replace modem Investigate how to get on internet (Freewave to somewhere) Pay for DSL phone line? Communications at MAIR Find internet point of presence where we can piggyback PTGV, MACC, MCTY, PIGT, CVMS, HCES - OK for now. * confirm that contact at internet point of presense understands that we need to connect to the GPS receiver/our router from outside รป has to be a public interent address.
ETN
Station Maintenance
John was on vacation. Jim and Chris provided an update.
May trip was a success. Want to schedule one per month for
the next 3 months and finish things up.
CCRT is fixed.
Flat gap is done.
Van Hill is done. Holly says this is a very good station.
Greenback E/W sensor is replaced.
Van Hill gate got bull dozed. Need to replace it when they're done
working.
Next trip will be CCNC install and repair at GFM and TRYN. Tentative
date is July 9-13.
MGNC interference magically dissappeared.
Still might be a problem at SMNC.
TZTN needs a gate.
Network Completion
The map shows stations
with yellow triangles being new ones.
station | man-days | status |
---|---|---|
MGNC | 8 | done |
CCNC | 8 | new |
WSSR | 8 | new |
TVNC | 8 | new |
VHTN | 8 | done |
RBNC | 4 | done |
TRYN | 4 | done |
GFM | 4 | done |
SMNC | 4 | done (see note above) |
PLVA | 2 | abandon |
BHT | 8 | move (eventually) |
Routine Maintenance Kudzu, battery check, etc, etc.
Second Tier Priorities
ANSS.
C2SC was back and is down again.
CVTN and ASAR optical isolation. Need to upgrade to year 3 hardware.
Hardware ready.
CVTN is awaiting a new ip.
NAIT is the only non-real-time station. Wish to get it
online. Might be able to hit Richardson from there.
NWS has new ups. They would like us to plug into that and remove
our ups from beneath the rack. Bill will take care of it.
Lenox Agreement. We have new contact info. Mitch will see if a new MOU is desired.
FDL.
There is a new FDL Policy.
.
Bill reports that his laptop works well with the equipment but the others
do not. Steve will show him how to get the others set up like his.
Steve has boot floppies and instructions for downloading data from
the multi-channel seismograph without using the NT domain (which is defunct).
The images and instructions are also available at
/gaia/data/fdl/strataview.boot.floppy.
As Time Permits
3890 Power
Chris is going to make a diagram for 3890. Good luck son.
Generators
P-plant was over the other week and, to our surprise, ran the generator
(the new one). Greg informed them that it runs automatically every
Monday morning. Not really a good idea to run it under no-load anyway.
Doesn't really solve the need for routine mainenance like oil and
filter changes, etc. Mitch will try to find out what their plans are.
Inventory
Jim has all the broadband sensors defined and is working on additional
equipment (e.g. isis) and the connections. Mitch will install Bill's
account in mysql and inv so he can start building stations. Mitch needs
to sit down with Jim and figure out what we need to have ISTI help
us with. Sid will be available after about mid-May to finish up anything
we need his help to take care of. Apparently the downloaded docs from
guralp for the cmg5td's have the old +-4g contants. Mitch has paper
documentation with the correct +-2g constants.
Steiner Brain Dump Seminar
Marathon week while John was in Memphis. Completed 12 sessions
so far. Can fit 1 hr/dvd and each dvd is 4.5 GB. Have about
12.5 hours so far. Would be nice to get these online. How
public should they be?
Other
SLU BB Stations.
UTM is roughed in. Wurth needs to complete.
Poplar Bluff is done. The E/W channel in the sensor is bad so it
needs to be replaced. Mitch will find out the scn and get them
to add it to the ew export.
Thin-wire aironets are no longer available. This will be a problem for the DBB. It will need to be addressed hopefully later rather than sooner.
All hardware is in house to replace the node computers in the coming year.
We'll upgrade to ew v7.1 at the same time. This means we'll be using
scnl instead of just scn. Steve, Al, and Mitch are working on the details
(headaches) of that. Glasworm is the converter and is operational with
the new switches.
Note that the new MTTN node pc is the exception. We're not ready for
it to be scnlized yet.
MPHB. Withers needs to determine current orientation so we can pull it and orient correctly. Helicorders look strange. Need to verify the data. Recentered, data are fine now.