Tech Staff Meeting Notes March 13, 2007
Current Top Priorities are:Station Maintenance. SLU stations. (Also wish to get INV populated.)
There are four levels of priority.
Priorities | Wish to try to get these done (or make progress on) before the next meeting (yeah right) |
Second Tier | Fit this in too if an opportunity arises. May be good to do instead of priorities but check with Mitch. Likely to be a priority in a previous and/or subsequent month |
As Time Permits | Fit these in when you can but not instead of first or second priorities |
Other | Stuff we hope to get to and don't want to forget about |
This task list as of September 12, 2006. Note that everyone is still needed to work on essentially all tasks. There is however, a single person who is primarily responsible for each one. Mitch of course, is ultimately responsible for everything.
Priorities
Station Maintenance, NMSZ
Jim noted that the /stations page is out of date and in several cases, wrong
The signal strength at lnxt and mkta is deteriorated which could be
causing alot of the problems in the bad channel list. The transmitter
at sftn for the mkta analog backbone was replaced.
The receivers are drifting and we need a wholesale general retuning.
Bad Channel List 20070206:
Channel is Out
GRAT.EHE
MCAM.EHN
CPAR.EHZ
QUAR.EHE
Sporadic Outages
CHRM
RDGT
HOVM
BFAR
DLAR
COKM.EHE
BROM.EHE
Drifting/Harmonic Problem ?? (Magically dissappeared, I hate it
when that happens).
DLAR.EHE
TIPT.EHZ
BRGM.EHE
SLU BB Stations. Little Rock week of 3/19. Poplar Bluff and Martin next. Should take about 3 days each. The 4th near Springfield, MO is permitted but needs to be sited. Need to get all this done by the end of April. So no crying about the rain.
Lenox Agreement. Should be ok. Its wait and see for now.
GPS
Planning to purchase new receivers for all stations (some are quite old).
Done.
Steele is now on AC.
(NWCC)
We'll be making a wireless radio shot with two Freewaves, the base at the
Tiptonville Highschool and the slave at the prison. The radio can go into
the existing GPS enclosure, while we'll mount the antenna on a tripod on the
roof of the MIS building. Chris and James are working on a shopping list for
parts.
At the highschool, we'll install a Freewave antenna and coax onto their
sixty-foot tower. The coax will be run into the shop classroom and into a
radio enclosure placed high enough to be out of reach. School maintenance
has offered whatever help we might need, including running power and Cat-5.
This is part of the "getting-sites-in-Lake-county-online" scheme using
Freewaves to relay data back to the highschool.
The plan is still to repeat RLAP through New Markham (tenatively being
called NMKM). We won't know for certain if the beacon tower will allow us a
straight shot to Tiptonville until we can do radio tests when the trees are
fully foliated.
Moving our receiver enclosure to the beacon tower means trenching new coax
for the antenna. This will likely be hard-line with lightning arrestors on
both ends.
The old electric drop to the tower is corroded and unusable. We'll be using
solar, here. Bob's also mentioned placing both the enclosure and solar panel
high enough up the tower to deny the curious quick access, perhaps eight or
so feet.
NMKM was already go, but now the second new site in Tiptonville has been
located at the highschool. The next step is up to Bob and John-Paul -
installing the deep drill-brace monuments. After that's done, the receivers
and other stuff can go in.
ETN
Station Maintenance
SMNC frequencies were changed. There is an additional problem. What is it?
CCRT has a large dc offset (permanently in the lowest gain setting) which
causes trace to appear flat unless data are visually magnified. Also
causes premature saturation on one side. Unfortunately the park is closed
until April.
TZTN needs a gate and the gps antenna swapped. Have the antenna.
GFM has a cable problem. Will visit in the spring.
Have some Lexan and batteries to give John.
MGNC appears to be experiencing some kind of interference.
The MYNC.US saga continues. Meremonte suspects the VSAT gateway.
He's sending the entire stack for swap. John will need to flash
the DRU with the DW4020 firmware and replace the stack.
Network Completion
The map shows stations with yellow triangles being new ones.
station | man-days | status |
---|---|---|
MGNC | 8 | done |
CCNC | 8 | new |
WSSR | 8 | new |
TVNC | 8 | new |
RBNC | 4 | done |
TRYN | 4 | done |
GFM | 4 | done |
SMNC | 4 | done (see note above) |
PLVA | 2 | abandon |
BHT | 8 | move (eventually) |
ANSS.
CVTN and ASAR optical isolation. Need to upgrade to year 3 hardware.
Hardware ready. James brought back some
nice pictures from CVTN to help figure out how to do it (e.g. the
conduit is way too small).
NAIT is the only non-real-time station. Wish to get it
online in 2007. Might be able to hit Richardson from there.
Routine Maintenance Kudzu, battery check, etc, etc.
Second Tier Priorities
Steiner Brain Dump Seminar
Marathon week while John was in Memphis. Completed 12 sessions
so far. Can fit 1 hr/dvd and each dvd is 4.5 GB. Have about
12.5 hours so far. Would be nice to get these online. How
public should they be?
FDL.
Got the new laptops. These are the rules:
They will all be configured exactly the same. Old laptops will be
obsolesced NOT retasked. Each of the new ones will have a primary
purpose (though if they're all the same, they should be able to fill
all other purposes in a pinch):
3890 Power
Chris is going to make a diagram for 3890. Good luck son.
As Time Permits
Generators
Since P-plant doesn't seem to be helping maintain anymore, Bill is
now the generator guy. As a start, he'll run the old generator
monthly.
Inventory
Jim has all the broadband sensors defined and is working on additional
equipment (e.g. isis) and the connections. Mitch will install Bill's
account in mysql and inv so he can start building stations. Mitch needs
to sit down with Jim and figure out what we need to have ISTI help
us with.
Other
All hardware is in house to replace the node computers in the coming year.
We'll upgrade to ew v7.1 at the same time. This means we'll be using
scnl instead of just scn. Steve, Al, and Mitch are working on the details
(headaches) of that. Glasworm is the converter and is operational.
New switches for the scnl trace-wire are in house. Steve will install. Done.
I-40 Bridge. MPHB. Withers needs to determine current orientation so we can
pull it and orient correctly. Helicorders look strange. Need
to verify the data. Recentered, data are fine now.
VBMS. VSAT issues resolved. Install planned for March or April.
Brent Rosenblad from Mizzou (?) wishes to perform active source reflection
profiles at 8-10 sites again this year.
Wound up doing regrading with significant manual assist. Need an
eight inch extension for the surface vault.
Pumped the water out of the holes. Found sixty feet of sand
in the 200 foot hole. This was done to weight down casing
during install and never removed. Doh! Driller will
remove it.
Greg will arrange and supervise regrading of HDBT. The regrading
was started and there were, shall we say, problems (more like a CF).
Hopefully the contractor will have better luck next time.