Tech Staff Meeting Notes February 6, 2007
Current Top Priorities are:Station Maintenance. (Also wish to get INV populated.)
There are four levels of priority.
Priorities | Wish to try to get these done (or make progress on) before the next meeting (yeah right) |
Second Tier | Fit this in too if an opportunity arises. May be good to do instead of priorities but check with Mitch. Likely to be a priority in a previous and/or subsequent month |
As Time Permits | Fit these in when you can but not instead of first or second priorities |
Other | Stuff we hope to get to and don't want to forget about |
This task list as of September 12, 2006. Note that everyone is still needed to work on essentially all tasks. There is however, a single person who is primarily responsible for each one. Mitch of course, is ultimately responsible for everything.
Fourth Annual Feast of Flesh will be Friday February 23, 2007 at 6:30
at the Butcher Shop on Germantown Road.
Priorities
Station Maintenance, NMSZ
Lenox Agreement. Need to verify that we'll still have use
of the SCA with new occupants.
GPS
ETN
Station Maintenance
SMNC frequencies were changed. There is an additional problem. What is it?
Network Completion
The map shows stations
with yellow triangles being new ones.
ANSS. Routine Maintenance.
Second Tier Priorities
Steiner Brain Dump Seminar
Held the first one in January. Mitch concedes defeat attempting to
automagically create a written document from the voice recorder.
We're exceeding the design specs by recording an entire room of
people. Jim made a video which is the better way to go. Next
one is tentatively scheduled for week of Feb 12 if weather is
bad enough to prevent assisting SLU station relocating. FDL.
Got the new laptops. These are the rules: 3890 Power
Chris is going to make a diagram for 3890. Good luck son.
As Time Permits
Generators
Old generator needs an exhaust pipe.
Inventory
Jim has all the broadband sensors defined and is working on additional
equipment (e.g. isis) and the connections. Mitch will install Bill's
account in mysql and inv so he can start building stations. Mitch needs
to sit down with Jim and figure out what we need to have ISTI help
us with.
Other
All hardware is in house to replace the node computers in the coming year.
We'll upgrade to ew v7.1 at the same time. This means we'll be using
scnl instead of just scn. Steve, Al, and Mitch are working on the details
(headaches) of that. Glasworm is the converter and is operational.
New switches for the scnl trace-wire are in house. Steve will install. I-40 Bridge. MPHB. Withers needs to determine current orientation so we can
pull it and orient correctly. Helicorders look strange. Need
to verify the data. Recentered, data are fine now.
VBMS. ASL crew will install sensor, das, and vsat in November.
Problems with the VSAT carrier delayed installation...the saga continues.
There is a new chair at ASU in Jonesboro and he's interested in getting a
modern display for Laredo. Mitch is deciding what to do.
Brent Rosenblad from Mizzou (?) wishes to perform active source reflection
profiles at 8-10 sites again this year.
Greg will be with Wurth next week (week of feb 12) to investigate resiting
carbondale and ut martin. Herrmann has some specific ideas about where
he wants them to go to get more quiet installations. There are 3 other
stations (little rock and two new ones) that they need help with and
need finished by April.
Jim noted that the /stations page is out of date and in several cases, wrong
Previous notes report that 7 stations contained many glitches and
were removed from the trigger groups on mainworm. Only RDGT appears
to be this way so we'll add them back in and see how it goes. The
issue with the grounding problem (or lack of it) between bottom
of the ISIS canister and the copper springs appears to have magically
dissappeared. Possible something shook things up to reestablish the
ground. I bet it reappears some day.
The signal strength at lnxt and mkta is deteriorated which could be
causing alot of the problems in the bad channel list. The receivers
are drifting and we need a wholesale general retuning.
Bad Channel List 20070206:
Channel is Out
GRAT.EHE
MCAM.EHN
CPAR.EHZ
QUAR.EHE
Sporadic Outages
CHRM
RDGT
HOVM
BFAR
DLAR
COKM.EHE
BROM.EHE
Drifting/Harmonic Problem ??
DLAR.EHE
TIPT.EHZ
BRGM.EHE
Planning to purchase new receivers for all stations (some are quite old).
Power was turned off at the Steele site and it is unknown if or when it
will be restored. Current plan is to convert it to solar using 1 100ah
battery and 1 120W panel (about 28" by 4'). Assuming a station draws
4W this should provide about 4-7 days backup. It'll work but is probably
pushing it over the dreary months and there may be outages and battery life
may be reduced.
Freewaves are on order and should arrive next week.
Have permission to move everything (except the mount of course) to the beacon
tower at Reelfoot. Antenna needs to stay below
the beacon (should provide around 40 to 50 feet elevation. Previously
had planned to repeat through New Markum (a new station John Paul's putting
in) and on into Tiptonville H.S. On the beacon tower, might be able to
make it without the repeat. This is going to require a long heavy wire
with very careful and robust lightning protection.
CCRT has a large dc offset (permanently in the lowest gain setting) which
causes trace to appear flat unless data are visually magnified. Also
causes premature saturation on one side. Unfortunately the park is closed
until April.
TZTN needs a gate and the gps antenna swapped. Have the antenna.
GFM has a cable problem. Will visit in the spring.
Have some Lexan and batteries to give John.
MGNC appears to be experiencing some kind of interference.
John's spectrum analyzer is unfixable and was obsolesced. Prefer to wait
til the end of the budget year (fall or winter) to replace it. Will have
to take the one from Memphis when needed.
station man-days status MGNC 8 done CCNC 8 new WSSR 8 new TVNC 8 new RBNC 4 done TRYN 4 done GFM 4 done SMNC 4 done (see note above) PLVA 2 abandon BHT 8 move (eventually)
GPS pods changed at ADSC and TRSC. SHTN is the only one left. Done.
CVTN and ASAR optical isolation. Need to upgrade to year 3 hardware.
Hardware ready. James brought back some
nice pictures from CVTN to help figure out how to do it (e.g. the
conduit is way too small).
CUSEC now has business class DSL and an ip address for CUET. May need
to get a switch to hang between the dsl router and the mss100. Steve
will visit to determine hardware needs. Done and online.
That leaves NAIT as the only non-real-time station. Wish to get it
online in 2007. Might be able to hit Richardson from there.
They will all be configured exactly the same. Old laptops will be
obsolesced NOT retasked. Each of the new ones will have a primary
purpose (though if they're all the same, they should be able to fill
all other purposes in a pinch):
Presumably 1 and 4 could be secondary for each other and 2 and 3 could
be secondary for each other.
Greg will arrange and supervise regrading of HDBT. The regrading
was started and there were, shall we say, problems (more like a CF).
Hopefully the contractor will have better luck next time.