Tech Staff Meeting Notes October 9, 2006
Current Top Priorities are:LNXT Node BB upgrade, Station Maintenance, and ET Stations. (Also wish to get INV populated.)
There are four levels of priority.
Priorities | Wish to try to get these done (or make progress on) before the next meeting (yeah right) |
Second Tier | Fit this in too if an opportunity arises. May be good to do instead of priorities but check with Mitch. Likely to be a priority in a previous and/or subsequent month |
As Time Permits | Fit these in when you can but not instead of first or second priorities |
Other | Stuff we hope to get to and don't want to forget about |
This task list as of September 12, 2006. Note that everyone is still needed to work on essentially all tasks. There is however, a single person who is primarily responsible for each one. Mitch of course, is ultimately responsible for everything. Mitch is going to update this shortly.
Priorities
Lenox Agreement. Jim noticed the 12 year agreement for the LNXT node is about to expire. Mitch will renew.
BB network upgrade.
All sensors with new top-caps have the Steiner blessing.
See Mitch's PDF
webpage for results.
Only LNXT stations remain. LNXT cr is done. LNXT station is done.
PEBM and GLAT on deck. HALT needs a 50' tower. Prefer to spend the
cash and do it right rather than put up a flimsy stick.
GPS
James will coordinate with Bill or Chris when he will be going to
the field and needs assistance.
Notes from James:
Firstly, the radio tests in and around Tiptonville are complete. We'll likely do a relay shot from RLAP to New Markham, and then bring both sites back to the highschool in Tiptonville. We have permission from the school to use their 50' tower on-site. We'll need a second shot from our site at the Corrections Complex (NWCC) to the highschool. For this, we'll need either a roof or building mount antenna at at least 30' height. The MIS building itself (where out stuff is) can give us almost twenty feet. We'll need to buy high-gain antennas and mounting hardware, and some _serious_ lightning protection.
The second set of radio tests will be at Steele, Missouri, hopefully on 10/20. I visited this last Friday and spoke again with superintendent Mitchell Fisher. WREG has a short mast on one side of the administration building of the Steele schools for their weather station. I'm going to email our contact there to see if we can mount our antenna on that mast. The building's mechanical room has roof access and plenty of space for our radio equipment enclosure. Bob seems to be waiting for the results of this test before he buys radios and antennas.
We've not been able to secure permission to get back inside the terminal building at RLAP. To winterize the station, we need to replace the five aircells with another solar panel, battery, and a charger that will take two panels. Sure, we could trench AC power out to the station, but that would be wasted effort if we _do_ get permission to move back inside. Meanwhile, having the charger, battery, and panel hardware on-hand would be nice for one or both of our new sites around Tiptonville. Mitch and I are in agreement that we can't keep sponging off the seismic networks. We'll have to buy our own stuff.
ETN
The map shows stations
with yellow triangles being new ones.
SMNC may be getting interference and the gain channel is showing up on
the vertical (but doesn't look right). John will visit this week,
swap the radios, and inject a known signal on the pins.
station | man-days | status |
---|---|---|
MGNC | 8 | done |
CCNC | 8 | new |
WSSR | 8 | new |
TVNC | 8 | new |
RBNC | 4 | done |
TRYN | 4 | done |
GFM | 4 | done |
SMNC | 4 | done (see note above) |
PLVA | 2 | abandon |
BHT | 8 | move (eventually) |
ANSS. Routine Maintenance.
Unscheduled Maintenance
Second Tier Priorities
Need to follow up on ATV training. DONE. NCCU
Gordana Vlahovic is getting a cmg6td to install at North Carolina
Central University. Invoice paid. Still owe here a vault (John
has it) and installation advice. Need to get a public display.
Scream to Scream from the datalogger pc to the display pc would
be best. Don't forget to NOT allow remote config on display scream.
John will be doing this later this month. Done. Data are flowing into
scream at NCCU. Al will get with Gordana to get the NCCU scream transmitting
to the mudworm scream.
Steiner Brain Dump Seminar
Gregs list is starting to take shape. While anyone is invited its
geared to tech staff. Schedule will vary and be weather dependent
to avoid field work interruptions. Will start within a few weeks. FDL.
Mitch needs to talk with Horton about what to do about FDL laptops. Clearly
we're not getting help from Bodin. 3904 Power
Need to draft an updated wiring diagram of 3904. Need to update the
diagrams on the circuit panels. Greg put up signs on the panels
with a call down list.
As Time Permits
Mitch needs to write an ew module to monitor the environmental channels
newly installed at the nodes. Done. Its a shell script that runs
twice a day. Computes several minute averages. Emails when there's
a problem. Its is /gaia/home/mwithers/Projects/ENVMonitoring.
Need to come up with a good way for John to view real data (not helicorders)
on is pc over dsl. Mitch will send John info on ssh and exceed.
Generators
Old generator needs an exhaust pipe.
Inventory
Sid has Ketchum's INV program installed on smeagol. Jim got initial training.
Need to show Bill how to use it. Jim will be the lead and Bill will do
initial update. Routine updates can be done by whoever does the work (requires
usernames and passwords in mysql). Not sure yet how best to handle dataless
seed production. Mitch needs to learn the admin tasks. Startup script is
/gaia/smeagol/local/bin/runINV. Mitch will find out from Meremonte how
they do site contacts, directions to station, etc, etc.
Other
Many of the air cells in storage are ancient and bad. Bill will
go through them and dispose of the old. Greg has method for safe
and legal disposal.
I-40 Bridge. NHIN. MPHB. Withers needs to determine current orientation so we can
pull it and orient correctly. Helicorders look strange. Need
to verify the data.
VBMS. Vault is done. Contractor work is complete. Alena says
sensors might be available in a month but NEIC staff is currently tied
up with carribean net (tough job but someone has to do it).
Langston Zack. Greg's list said to test accelerometers
and mass produce hardware. This is wayback burner. Mitch will check
with Chuck to verify that its even going to be done anymore.
Mitch asked and its unknown. Strike from list.
Bill is getting familiarized with these so he can take them over.
John upgraded gps firmware at 2 of 3 gps. Mitch doesn't recall which
ones. John says Knoxville and 2 in charleston still need upgraded. This
is the list from before:
SWET-3H52, ADSC-5657, and CSTN-5637 need to have the leap second
corrected. SHTN-5648 and TRSC-5662 might also but need a site
visit to verify.
Mitch needs to contact UKY tech to get a site visit to MVKY.
ATTN is having firewall problems. This is fixed but by accident.
Probably will come round again.
SFTN and RDST need a sensor swap.
Jim and Bill fixed a bunch of these. Mitch isn't sure which. Some of
work fine in the shop; Greg will have a look. Here's
Holly's list from the last meeting:
It isn't clear what's going on with a bunch of these. They work on
the bench and there aren't any measurable problems in the field.
Greg will take a look.
LNXT Node:
BRGM.EHZ
PLAR.EHE & .EHN
NMAD Node:
BACM.EHE
CHRM
COKM.EHE
FLPT
POBM.EHZ
TIPT.EHZ
TOPM.EHZ
MCAM.EHE
MKTA Node:
BLAR
BOAR
How do we record this for posterity? Video would be enormous in size
(potential of 104 hours or more of video). Audio might be useful but
would not make a very good reference. Mitch thinks written is best preferably
in html or pdf. Perhaps have someone (who) take everyones notes and
combine them with Greg's notes and make a web page. Audio/video cache to help
clarify might be useful for whoever does this. Mitch will ask the folks
at the ALC what they recommend.
Bill is now the designated battery czar.
Bill is in charge of everything in the fdl. He'll be developing SOP's to
keep track of who has what where.
Greg will put an SOP for dummies on the transfer switch.
Boreholes are drilled and more or less secured. Need to do prep
for new instrumention at HDBT and take care of drainage now that
a big pile of stone and dirt was piled around the station.
Greg's theory is lightning is clobbering gps. Has suppression
constructed and ready to install.
Need a better pc at AZTN now that we have equivalent of two nodes plus
going through it. Guralp hardware is on order. Steve and Greg will
knock heads to decide on telemetry to aztn (18+ channels will exceed
950Mhz bandwidth).
Got the modem and internet works. Need to integrate into CERI
central processing.