Tech Staff Summary 7/9/01
Current Priorities in addition to routine tasks
DBB
Tower at Shelby is up. Still need to align with MKTA and add
feed lines for ANSS station.
Still need permissions on Edith, Mitch will rattle chains in Nashville like
that will do any good.
No word yet from Falcon but won't be a problem.
The priority is to get the link to Marked Tree going.
ANSS
Vaults will be in around July 27. Various Steiner gizmos are prototyped.
Device servers are on order. NSMP stations at Hayti and Dyersberg will
go in week of July 16, Arnie Acosta will install and we will provide
an assistant.
Routine Maintenance
There are 12 LNXT node stations left to do. Several stations weren't
done due to access problems.
NSN
LRAL is up.
ET
Mitch has installed new mondo disk on gollum and will move it to
rnbworm to provide space needed to add MTTN stations and future DBB.
John is waiting on callback from cable company for Cumberland Gap.
John will call Steve to coordinate Athens alternatives. Need line
of site with Star Mountain and some kind of continuous connection.
Steve found out that Athens does have a nailed up ISDN with an ISP
and is looking into options to at least get picks out to the world.
Will require a normal node in Athens and removing the two BSD boxes.
These are John's goals for this field season (wagers on whether he gets it all done?):
Routine Maintenance
Finish building shop
Clean out our stuff at CEH
Repair GFM
Repair TRYN
Repair RBNC
Repair PLVA
Make Adjustments at BRBC
Determine if High Peak needs to be used after tweaking transmitters and
antennas, if so, re-occupy High Peak
Install helicorder at Lenoir Rhyne College
Assemble and align Panda II boxes
Install CMGA
Redo GMG
Install BRDT
Install MRTN
Install CPRT
Install fgtn
Install GCVA
Permission and Install ??KY
Permission (in works) and install CCRT
Finish installing sensor at NC A&T
Permission and install station at Wayah Bald NC (WYNC)
Remove batteries and box at WSSR
Rebuild catwalk and railings at ETT
Repair/Relocate RICH
Repair SMNC (Requires the use of a spectrum analyzer and then getting rid of
the interference)
Install station for Appalachian State University (Boone, NC)
ISIS II
Will keep pluggin away as time permits.
I-40 Bridge
Ongoing.
Second tier priorities
Some stations on analog backbone gain-ranged during the Conway event and
aren't supposed too. Mitch will figure out which ones and give list
to Greg.
Marion, LA
New CMG40T site
PII
Need to test and calibrate 15 units on CERI campus before summer
Then inventory P/PII on South Campus
Then cannabalize whatever is necessary from P/PII to get 15 stations going by
end of summer
Then cannabalize whatever is left to get as many others operational as possible
RAMPS shakedown forced initial assessment and it ain't looking good.
LDEO
Need to verify that software works.
Downloads on Shelby Forest.
Power Supply for Fort Pillow.
RAMP
Enola deployment is over. Beats me how we're going to repair/service.
War Room
Mitch will produce a station map for the ANSS-MA region
Greg acquired raised relief maps and will replace the nasty old map.
LNXT node
Secure propane tank.
Secure racks.
replace coax jumpers
replace rg-58 unshielded jumpers
MKTA node
NMAD node
IRIG SOH.
Need to record the SOH channel from the gps clocks to know when sync is
lost (they will continue to produce IRIGE based on internal clock).
Greg has added channel to monitor gps clock. Need an ew module that monitors
and complains.
Backburner priorities.
Board Shop
A few details yet to finish.
At least for this month, we allegedly don't need a shower.
Station book.
Steve installed earthworm v5. Word is, the schema changed again but
this shouldn't prevent us from populating with meta data.
Status channels. Currently supplied on last 8 channels. Need a module to process.
LNXT node
These stations are on indefinite hold until we see how the fit
with pending ANSS plans.
permit/install L7 and L8
MKTA node
These stations are on indefinite hold until we see how the fit
with pending ANSS plans.
permit/install remaining 3 ISIS.
NMAD node